Ripples over multi billion naira Apapa Port Terminals’ project
The redevelopment contract of Bullnose I,II and III terminals in
Apapa, Port Complex by the Federal Ministry of Transportation and
Nigerian Ports Authority (NPA) awarded to Eko Support Services (ESS) in
2008 at $124 million (about N40,920,000,000) is causing ripples in the
maritime industry.
Maritime stakeholders said they were uncomfortable, not only with the
cost of the contract, but also the process that led to the award of the
project to ESS which they alleged was shrouded in secrecy.
The push for the redevelopment and the award of the contract which
was through a letter from the Managing Director of NPA dated 3rd of
June, 2008, to the then Minister of Water /Transportation, was said to
have been done in response to Federal government’s initiative for
private sector participation in ports development.
But maritime watchers opined that in line with due process and
transparency, the initiative should have gone through a public tender to
afford other interested private sector players the opportunity to bid.
Officials of the Federal Ministry of Transportation last week declined
comment on the issue. The NPA also refused to comment on the controversy
over which some stakeholders are contemplating petitioning the
Presidency, the ICPC, and the Bureau for Public Procurement which vets
awards of contracts. They argued that since it was government’s idea
that the private sector should be involved, then it was only fair that
the contract award and pricing, should also have been subjected to
private sector participation.
A maritime industry insider said it would be difficult not to assume
that the beneficiary firm was handpicked by the awarding authority.
‘’Obviously, the NPA handpicked ESS and went ahead and recommended the
company for this project,” the insider said, wondering why the
supervising ministry did not raise any issue on the process leading to
submission of the proposal by only ESS.
It was learnt that in the proposal, ESS offered to handle the project
at a cost of $127 million, but that following what the then NPA boss
said was the approval of the proposal by a Technical Committee and
vetting of the proposal by NPA’s Technical Channel Auditors, Messrs
Coastal and Reclamation Engineering Services, (CARES), NPA recommended
that the project be scaled down to $124 million, indicating a margin of
just $3 million lower than what ESS proposed.
Said the insider: “Even by today’s standard, that redevelopment
project could be achieved with a little over $50million,” stressing that
a technical audit of what is on ground would tell you vividly that this
is not a project that should cost what was allegedly approved.
Also being contested by ports observers is the fact that the project
cost would be amortized through service boat charges in all the ports in
Nigeria. “In simple term, said an investment analyst, NPA has awarded a
Terminal redevelopment project to, as the insider put it, “ a so-called
private player, with NPA providing the exorbitant and inflated cost of
contract, through charges collected on behalf of NPA by the contractor,”
adding, “yet NPA will not have control of the Terminal for 25 years.”
What that means, the insider explained, is that the facility will be
used exclusively by the same contractor for the quarter of a century.
Other stakeholders, in picking holes with the contract, pointed to
loopholes with regards to the estimated cost of $124million recommended
by CARES, with the proviso that it is accepted pending the determination
of the actual cost from the final design; that the cost of financing of
16 per cent be applied to the cost of the project and hat the lease
should be for an initial period of 25 years.
The stakeholders argued that the term which says $124million is
accepted pending the determination of the actual cost from the final
design is loose, What would then happen if the winners now make a
detour, and insist from the final design analysis, that the cost has
increased by 200 per cent, they queried?
They said on balance the development is quite troubling. “Since the
money will be amortized from the service boat charges which belongs to
NPA and is a sure stream of inflow, why should the cost be this high?
they queried, saying the more crucial implication is that both the cost
of the project plus the cost of financing put at 16 per cent would be
borne by the Nigerian Ports Authority.
“Since that contract was signed the government may have incurred an
interest charges equivalent to over 100 per cent of the $124 million
price tag claimed by ESS. Ultimately this company could collect as much
as $500 million for a project that its real cost should not be more than
$50million. This is very saddening because there are even investors
that are ready to acquire these terminals and redevelop them with their
resources, not using government money and charging government interest
on it,” another NPA insider said.
Another insider said it is because of alleged anomalies like this
that experts have always called on Federal government to beam its
searchlight on the running of the ports from 1999 to 2010.
They said past governments made efforts to bring sanity to the
sector, but such efforts appear to have ended up being frustrated by
top government officials with more than professional interest in such
questionable transactions.
Post a Comment